Why does nobody talk about how much panel swaps changed after the 2020 code push
Honestly I did a panel replacement last week in a 1998 build here in Columbus and it was almost a different job than the ones I did back in 2019. Back then a swap was maybe 4 hours, pull the old can, land the same circuits, done by lunch. Now I'm looking at 6 to 7 hours because of the surge protection requirement and the extra grounding and labeling stuff the inspectors started checking hard after the 2020 code cycle hit. My inspector in Franklin County told me he flags about 3 out of every 10 panel jobs now for missing arc fault labeling alone. The wires didn't change, the houses didn't change, the paperwork and parts list did. Curious if you guys in other states are seeing the same stretch or if it's just my county being picky.