Can we talk about how my change order rate hit 38% and I feel like I'm running a different business now?
So I finally pulled the numbers on my last 14 months of work, mostly mid-size tenant buildouts around Charlotte, and my change order rate came out at 38% of original contract value. That floored me. For the first ten years I ran maybe 8 to 12% and thought that was normal. What changed was I stopped eating the little stuff. Every time a GC told me to just handle a small reroute or add a couple of outlets without paperwork, I started writing it up, even for a $400 item. Sounds annoying, I know. But it turns out all those tiny verbal asks were adding up to real money and real hours I was just donating. My crew stopped getting pulled off schedule too, since the GC now has to actually think before asking. The weird part is two of my regulars got mad about it at first, and one of them hasn't called me back in 4 months. I'm not sure if 38% is a healthy number or if I'm now the guy everybody dreads calling. Any of you track this? What's a normal range in your market?