Shoutout to the GC who swore the punch list would take 2 days and it took 11
We had a retail build-out in Columbus that was supposed to wrap with a 2 day punch list, but the fire marshal flagged 14 items on the alarm trim and we spent 11 days chasing parts and re-inspections. Some guys on my end say we should have caught it in the pre-walk and it's on us for trusting the sub's sign-off, while others say the marshal just moved the goalposts. Where do you all draw the line between your crew's fault and a bad inspection call, or is it always on the GC to eat the schedule hit?